Quantitative Schedule Risk Analysis · Tower C — Substation & Civils

Prepared 18 Jul 2026 · RunMonteCarlo (runmontecarlo.com) · analysis performed entirely client-side — the schedule never left the analyst's machine

1 · Executive summary

The deterministic (single-point CPM) completion of Tower C — Substation & Civils is 24 Aug 2027 (255 working days). Monte Carlo simulation of 5,000 schedule outcomes — combining background duration uncertainty with 5 discrete register risks — indicates this plan has only a 2% probability of being achieved.

At the P80 confidence level — the level typically adopted for commitment — the completion date is 31 Dec 2027, a risk exposure of 93 working days beyond the deterministic plan. The exposure is dominated by: Ground conditions worse than expected (+65d), Switchgear delivery delay (+46d), Commissioning defects (+15d).

Deterministic
24 Aug 2027
P50
10 Nov 2027
P80 — commit
31 Dec 2027
P90
1 Feb 2028

2 · Schedule fitness attestation

This analysis was run on a schedule that was assessed against a DCMA-aligned QSRA-readiness check at import. Verdict: READY · score 100/100 across 16 activities.

3 · Method statement

Monte Carlo simulation (5,000 iterations, seeded pseudo-random sampling) over the project CPM network (16 activities; FS/SS/FF/SF logic with lag honoured; full forward/backward pass per iteration). Background duration uncertainty was applied as three-point estimates and discrete risk events sampled per iteration by probability of occurrence; opportunities modelled with negative impact. Where multiple risks strike one activity in an iteration they resolve deterministically: series impacts sum, parallel (overlapping) impacts take the single largest, and fragnet events insert their delay after the mapped activity so it propagates through network logic. Distributions in use: triangular, pert. Approach aligned to APM PRAM Guide and AACE International RP 57R-09 practice.

4 · Inputs audit

ItemValue
Schedule sourcedemo · data date 2026-09-01
Activities / ranged16 / 16 (100% coverage)
Register risks5 (4 threats, 1 opportunities)
Calibration presettypical (-10 / 0 / 25 % of planned duration)
IDRiskTypeProbDistMinLikelyMaxMapped to
R-01Late utility diversion consentTHREAT35%triangular102045A1050
R-02Ground conditions worse than expectedTHREAT40%pert153060A1020, A1030
R-03Switchgear delivery delayTHREAT30%triangular204080A1100
R-04Early possession grantedOPP25%triangular51015A1000
R-05Commissioning defectsTHREAT45%pert51530A1130

5 · Results — completion distribution

0%50%80%90%100%DETP50P80P906 Aug 202710 Nov 202731 Dec 202716 Jun 2028project completion — histogram (frequency) with cumulative S-curve
ConfidenceWorking daysDateΔ vs deterministic
Deterministic25524 Aug 2027
P102657 Sep 2027+10d
P5031110 Nov 2027+56d
P8034831 Dec 2027+93d
P903701 Feb 2028+115d

6 · Risk drivers (contribution factor)

RiskImpact on completionΔ days
Ground conditions worse than expected
+65d
Switchgear delivery delay
+46d
Commissioning defects
+15d
Early possession granted
-9d
Late utility diversion consent
+1d

Contribution factor = mean completion when the risk fires minus mean completion when it does not. Negative (green) values are opportunities pulling completion earlier.

7 · Criticality index

ActivityCriticality% of iterations critical
Mobilisation
100%
Site clearance
100%
Earthworks & excavation
100%
Piling
100%
Foundations & pilecaps
100%
Substation substructure
100%
Building superstructure
100%
M&E first fix
100%
Switchgear installation
100%
Cabling & terminations
100%

8 · Mitigation scenario comparison

The register's mitigation actions were modelled as a post-mitigation scenario and simulated with the same seed for a like-for-like comparison. The mitigation package buys 48 working days at P80 (37 at P50) for a combined action cost of £135,000 — approximately £2,813 per day saved.

ConfidencePre-mitigationPost-mitigationDays saved
P5010 Nov 202720 Sep 202737d
P8031 Dec 202726 Oct 202748d
P901 Feb 202811 Nov 202758d
RiskMitigation actionCost
Late utility diversion consentEarly engagement with utility; pre-application consent£15,000
Ground conditions worse than expectedAdditional ground investigation boreholes£40,000
Switchgear delivery delayEarly procurement + expediting agent£60,000
Commissioning defectsFAT witness testing + pre-commissioning checks£20,000

9 · Reproducibility

seed 8812 · iterations 5,000 · engine proto-0.1 · sampling: plain Monte Carlo · fitness READY 100/100
This analysis is exactly reproducible: re-running the same Risk File with the same seed and iteration count yields identical results on any machine.